Authorize Kraus-Anderson Construction Company to solicit bids for the Bielenberg Sports Center Expansion Project

 

SUMMARY

 

At the November 28, 2012 City Council workshop, plans for the Bielenberg Sports Center Expansion Project were reviewed and Council directed staff to complete the plans and specifications for the building project.  The next step in the process is to authorize Kraus-Anderson Construction Company to solicit bids for the project.  The bid date for the building construction, including the outdoor refrigerated ice rink, is planned for March 5, 2013.  The results will be brought to the March 13 Council meeting.

 

The landscaping, including the water play feature, is being coordinated as a separate project and bids will be solicited at a later date still to be determined.  Staff is working with Stantec to complete this part of the project and the preliminary plans will be reviewed at the February 20, 2013 City Council workshop.

 

RECOMMENDATION

 

It is recommended that the City Council authorize Kraus-Anderson Construction Company to solicit bids for the Bielenberg Sports Center Expansion Project as detailed in the plans and specifications.

 

BUDGET IMPACT

 

The total cost of the project is estimated at $21.8 million with funding from General Obligation Tax Abatement Bonds, Capital Improvement Fund, Park Dedication Fund, Storm Water Area Charge Fund and Utility Rebates as outlined in Attachment 1.

 

PUBLIC PROCESS

 

November 2012 / January 2013

Complete construction documents

December 2012

Review final site and buildings plans

December 12, 2012

Hold public hearing and approve abatement plan

December 12, 2012

Establish sale date for the G.O. Tax Abatement Bonds

January 23, 2013

Approve plans and set bid date


 

PUBLIC PROCESSContinued

 

January 23, 2013

Award the sale of the G.O. Tax Abatement Bonds

March 5, 2013

Accept bids

March 13/27, 2013

Award bids

April 2013

Start construction

February / March 2014

Complete building construction and open for use

April / June 2014

Complete site work, restoration and landscaping

 

 