CITY OF WOODBURY, MINNESOTA
Office of City Administrator
Council Letter No. 05 –
April 13, 2005
|
TO: |
The Honorable Mayor and Members of the City Council |
|
|
|
|
FROM: |
Clinton P. Gridley, City Administrator |
|
|
|
|
SUBJECT: |
Well No. 16 Phase I Approval of Change Order No. 1 |
SUMMARY
During the construction phase of Well No. 16, staff, contractor and consultants identified the need for additional traffic control beyond the original contract. In order for the contractor to receive payment, it is necessary a change order to the original contract be processed.
RECOMMENDATION
It is recommended that the Council adopt a motion approving Change Order No. 1 for the Well No. 16 Phase I improvements for E.H. Renner & Sons, Inc. in the amount of $1,065.87.
BUDGET IMPACT
This project is funded from the Area and Connection Charge Fund. Sufficient funds are available for this change order.
BACKGROUND
E. H. Renner has submitted Change Order No. 1 for the Well No. 16 Phase I improvements.
This change order provides for barricades installed on a pathway to protect pedestrians and to close a road for approximately two weeks while test pumping activities were being performed. The total amount for this change order is $1,065.87.
|
PROJECT ITEM |
CHANGE ORDER AMOUNT |
REVISED CONTRACT AMOUNT |
FUNDING SOURCE |
|
Change Order No. 1 |
$1,065.87 |
$228,665.87 |
Area & Connection Charge Fund ($295,000 – Phase I) |
|
Written By: |
Aaron, Nelson, Graduate Engineer |
|
Approved Through: |
David R. Jessup, Public Works Director |
|
Attachments: |
None |
|
File: |
13-2004-01 |